Awbeg Suite – CUH

The Awbeg Suite refurbishment at Cork University Hospital was delivered for the Health Service Executive to transform an existing ward area into a modern nine-bed patient accommodation suite. The €500,000 project was completed over a compressed 4 to 5 week programme within a live hospital environment, where continuity of healthcare services was critical.

The reconfigured layout included nine patient bedrooms, a staff base, nurse station and associated WC facilities. The scope of works involved extensive strip-out and demolition, asbestos removal, installation of new partitions, ceilings, wall and floor finishes, sanitary fittings, and full mechanical and electrical upgrades. Acting as Project Supervisor Construction Stage (PSCS), we coordinated the works to ensure strict compliance with healthcare, safety and infection control requirements. The project was delivered on programme and maintained an excellent safety record throughout.

Project Details

  • Client: HSE, Cork University Hospital

  • Budget: €500,000

  • Timelines: 5 weeks

Live Hospital Environment

All works were undertaken within an operational hospital setting, requiring meticulous planning and coordination to ensure there was no disruption to adjacent clinical services. Infection control procedures, restricted working areas and carefully managed logistics were central to the successful delivery of the project.

Fast-Track Delivery and Safety Performance

The complete refurbishment was delivered within an accelerated 4 to 5 week programme, meeting the client's tight timeline and budget requirements. As PSCS, we maintained a strong focus on health and safety, resulting in the project being completed on schedule with a clean safety record.

Next
Next

Blarney Watermains – Blarney Golf Resort